Cureton Caplan  
Home About Us Consultation Attorneys News Contact Us

New Jersey Construction
And Mechanic's Lien Law
 
- James H. Landgraf, Esquire

New Jersey has historically provided, by Statute, protection for certain construction contractors, sub-contractors, vendors and design professionals through the right to file a lien against privately owned property. Until April of 1994, these protections were provided through the New Jersey Mechanic's Lien Law, which is described later in this paper. In January 1994, the New Jersey Construction Lien Law was passed, effective April, 1994, and repealed and replaced the New Jersey Mechanic's Lien Law with respect to projects for which a construction permit was issued on or after April 22, 1994 and any improvements upon which work or services were commenced on or after April 22, 1994, if a construction permit was not required. With regard to any work for which a construction permit had been issued prior to April 22, 1994, or for which work had commenced prior to that date without the requirement of a construction permit, the provisions of the New Jersey Mechanic's Lien Law would continue to apply. Issues that would have arisen under the New Jersey Mechanic's Lien Law have now been effectively moot for the past four and a half years. The following shall concentrate on the current New Jersey Construction Lien Law (CLL).

NEW JERSEY CONSTRUCTION LIEN LAW

Neither the NJCLL nor its predecessor statute applies to public projects. Claims for which liens may be provided on public projects would be found under the New Jersey Municipal Mechanics Lien Law, which is discussed later in this paper.

Under the CLL (N.J.S.A. 2A:44A-1 et seq.), the filing of an MNI (Mechanic's Notice of Intent) is no longer necessary. To file a valid lien, it is simply necessary to file the prescribed information within 90 days following the date of last work, services, materials or equipment provision with the County Clerk of the county in which the property is located, owner and (if appropriate) the contractor/subcontractor who has failed to pay (N.J.S.A. 2A:44A-6). The Statute provides, within its language, a specific format and requirements for the lien claim notice (see attached forms).

The CLL has limited the amount of a lien claim by a number of parameters. Initially, a lien claim may only be filed when a written contract between the claimant and its customer (whether it be the owner, contractor or subcontractor) exists. In the event of a supplier, the written contract requirement may be satisfied by a purchase order executed by the owner, contractor or subcontractor or delivery tickets signed by an authorized representative of one of those entities (N.J.S.A. 2A:44A-2). The amount of the lien claim is then limited by the written contract amount for the work performed through the date of the lien, less credits for payments made. The lien claim may be expanded by the amounts of any written contract amendments or change orders which also must be reflected by written amendments to initial written contract. While the New Jersey Courts have not fully addressed the form in which an amendment to a written contract must exist, at the very least, a written work directive should be received from the claimant's customer. Recent cases have held that in the absence of a written contract or in the absence of written change orders, lien claims for monies that would be due are invalid. (Gallo v. Sphere Construction Corp., 293 N.J. Super. 558 (Ch. 1996) - where the Court held that the contractor had performed work during the pendency of negotiations for a written contract with the owner where the negotiations broke down and no written contract was entered, a lien claim cannot be filed for that work; Orefice v. ADR, 315 N.J. Super. 493 (A.D. 1998) - where the Court found that a lien claimant could not include within its lien claim, the amounts claimed to be due under change orders that were not reflected by any written amendment or agreement).

The amount of lien is further limited by payments that may have been made by the owner, contractor or subcontractor (N.J.S.A. 2A:44A-10). Obviously, any payments made to the lien claimant must be credited against the amount being claimed. Additionally, to the extent that the owner has made claims, has made payments to the contractor which have reduced the balance due under the contract with the prime contractor, the total amount of a lower tier lien claimants claim rights are limited to the contract balance due by the owner to the contractor. In other words, if the owner's contract balance obligation is $10,000 and a subcontractor's valid lien claim entitlement is $20,000, the total amount of the lien claim is limited to the $10,000 contract balance.

A party filing a lien claim is entitled to thereafter file amendments to that lien claim following the prescribed statutory form (N.J.S.A. 2A:44A-1). This most frequently arises in situations whereby a subcontractor or supplier has filed a lien claim for work performed, but continues to perform work under its subcontract or purchase order agreement. If the condition of non-payment continues, the cliamant entitled to amend its lien claim to include the additional value of that work performed.

Once a lien claim is filed on a private, non-residential project, a claimant is to serve that lien claim upon the owner and the party against whom it is claiming within ten (10) business days (N.J.S.A. 2A:44A-7). Service is to be made by personal service or certified mail, return receipt requested. Failure to so serve the claim within that period of time does not serve to discharge the lien claim, but an owner who may make payments between the time that the claim is filed and when it is ultimately served (if beyond the ten business days) may raise the claim that its rights have been prejudiced by the failure of the claimant to provide timely service. Additionally, the period of time within which the owner may have to seek response from the nonpaying contractor or subcontractor would not come into play in the absence of such service. Upon receipt of a lien claim, the owner is entitled to request that the contractor respond within twenty (20) days of service of the lien claim with any objection to payment under the lien claim (N.J.S.A. 2A:44A-12). If the contractor (or subcontractor in such event) fails to provide such written objection, the owner is thereupon entitled to make payment to the lien claimant and to receive a discharge of the lien. Such a payment can be credited by the owner to contract balance amounts that may otherwise be due to the contractor and the owner has a legal defense to any subsequent claims by the contractor that improper payment by the owner was made to the lien claimant.

A lien claimant will forfeit any rights that it may have to enforce the lien, and the lien itself is forfeited if legal action is not commenced in the New Jersey Superior Court within one year of the date of the last provision of work under its contract (N.J.S.A. 2A:44A-14). The one-year time period commences at the time of the provision of the last work or services, as opposed to the date of the filing of the lien. If such action is not brought within that time period, the lien rights are forfeited and the claimant is obligated to file within thirty (30) days a discharge of the lien (N.J.S.A. 2A:44A-30). Additionally, the owner or contractor against whom the lien claim is based, has the right to request, in writing, that the claimant commence legal action within thirty (30) days of the written request (N.J.S.A. 2A:44A-14). If claimant fails to file its legal action within that time period, notwithstanding that such time period may precede the overall one year limit, the lien rights are forfeited and the claimant is obligated to file the required discharge. If legal action filed by a lien claimant whether under the one year requirement or in response to a thirty day notice to be commenced in the Superior Court. The New Jersey Courts have been somewhat inconsistent with regard to division in which the action is to be commenced. There have been actions commenced within the Chancery Division as well as the Law Division with neither division taking a position that it lacks jurisdiction over the issues. A Notice of Lis Pendens must be simultaneously filed with the county clerk.

The lien statutes specifically allow for an exception to the otherwise standard New Jersey Doctrine of "Entire Case and Controversy". Although the parties involved in a lien claim may have additional issues (as an example, a subcontractor or contractor may have claims for additional damages that are not included in the written contract such as delay damages, acceleration claims, disruption claims, unapproved changed order work, etc.), the CLL specifically provides that such actions may be brought in a separate action, but does not mandate the same (N.J.S.A. 2A:44A-14). Further, where the parties may have entered into an agreement that includes an arbitration clause, it has been judicially interpreted that the arbitration clause will not control the lien claim. The lien claim action must still be commenced in the Superior Court and will not be precluded by the existence of an otherwise enforceable arbitration clause. Underlying disputes and disputes that would not be encompassed within the lien claim would still be pursued under the arbitration clause which could be operated simultaneously (with or without a stay of the initiated lien claim action).

The CLL has established sanctions for violation of its provisions (N.J.S.A. 2A:44A-15). The lien claimant who willfully overstates the amount of the lien or otherwise improperly files a lien claim or fails to file the required discharge of a lien claim once the claim has been satisfied or determined to be forfeited, may face sanctions including counsel fees and costs incurred by the owner or contractor defending the lien claim. Further, a party who fraudulently deprives a person entitled to benefits under the CLL would also be subject to sanction. This latter provision would include an intermediate contractor who may misrepresent to the owner the lien claimants status in the project, the amount claimed or other issues that could affect the lien claimants rights (N.J.S.A. 2A:44A-36).

If a lien claim is filed, the statutes alllow for a discharge of the lien by the issuance of a bond in the amount of 110% of the lien claim (N.J.S.A. 2A:44A-31). If such is filed, the surety essentially stands in the shoes of the defendant's on the lien claim.

The statute further provides the owner with the ability to make a request of the contractor or its subcontractors an accurate and full list of the names and addresses of each subcontractor or supplier who may have a right to file a lien pursuant to the act (N.J.S.A. 2A:44A-37). This list is to be verified under oath and reliance upon the list by the owner or the person who is requesting the same is deemed "prima facie evidence" to establish payments made in reliance thereon as well as defense to a claim that the party making the payments should have made additional inquiry to determine the identify of potential claimants. If the list is not provided in response to such a request, the person who was to provide the list shall be directly liable in damages to the requester for not only damages but court costs and attorney fees.

Under the CLL, it has been determined that universal waivers of lien claim rights are in violation of public policy and are therefore unenforceable except to the extent that a release of lien claim rights is issued for monies actually received by the potential claimant (N.J.S.A. 2A:44A-38).

The CLL is expansive in the listing of parties who have rights to file under its terms (N.J.S.A. 2A:44A-2). The following parties involved in a project have lien claim rights under the CLL: the prime contractors who have direct contractual relationships with the owner, licensed design professionals and/or construction managers having direct contractual relations with the owner; subcontractors to a contractor who has direct contractual relations with the owner; second tier subcontractors who have a contractual relationship with a subcontractor who is in direct contractual relationship with the prime contractor; and, suppliers including suppliers of rental equipment, who are in direct contractual relationship with either the owner, the prime contractor or the first tier subcontractor. Since a subcontractor is defined as a person "providing work or services in connection with the improvement of real property" under a contract with a contractor, and since "contractor" is defined to include licensed architect, engineer or land surveyor or certified landscape architect, who is in direct contract with the owner, design professional consultants providing services to the architect or engineer of record would similarly appear to have lien claim rights.

Lien claims may be filed to include work, services, material and equipment (N.J.S.A. 2A:44A-2). The term "work" under the CLL includes any activity, including labor performed in connection with the improvement of real property and further includes design services provided by salaried employees of a contractor or subcontractor. "Services" are defined to included professional services performed by architects, engineers, land surveyors or certified landscape architects who are not salaried employees of a contractor, subcontractor or the owner and who are in direct privity of contract with the owner for not only the preparation of plans and documents, but also for "studies, or the provision of other services". "Materials" include all goods delivered to or used on the site to be improved, materials or goods for incorporation into the improved property or for consumption as normal waste in the construction operations. It also includes materials that are used on the site in the construction or operation of equipment that is to be used in the improvement of the real property excluding fuel. Finally, "equipment" is defined as any machinery or other apparatus, including rental equipment, that is delivered to the site to be improved or used on the site to be improved, for incorporation into the improved real property or for use in the construction of the improvement of the real property.

Notwithstanding the very expansive definitions of what work, services, material or equipment may be included within the lien claim rights, certain caveats do exist. "Services" that pertain to professional design services will only include those services performed by a professional holding the specific license. Material will only include material that is actually delivered to the site and does not include material that may be withheld for non-payment, may be in fabrication, etc. A lien for equipment only arises after the equipment has physically been delivered to the site. While "work" includes the labor of salaried employees performing architectural and engineering services for a contractor or subcontractor, that definition does not include services by such salaried employees of suppliers. As a general proposition, since the CLL is a statutory creation, the New Jersey Courts have consistently determined that its language must be read narrowly and strictly construed. In other words, if a particular of work, service or equipment does not fall specifically within the allowable definitions, it will be excluded. If a party fails to meet the 90 day filing provision ( note that the 90 days is measured by calendar days and not business days) its failure will be strictly construed against it.

A lien filed under the CLL is a lien against the owner's interest in the property. It does not constitute a lien upon construction funds nor does it entitle a lien claimant to any "stop notice" protections against the owner making additional payments to the contractor. However, the owner does such at its own jeopardy to the extent that payment to the contractor after it has been served with a validly filed lien claim can conceivably subject it to an obligation to pay not only the contractor but additionally the lower tier subcontractor or supplier. A lien has priority over subsequent financing mortgage obligations as well as efforts to transfer the property. It does not have priority over any preexisting construction or purchased money mortgages. The lien may only attach to the property that is being improved notwithstanding that the owner may own other properties. By the nature of the statutory enactments, the lien claim will only apply to work, services, material or equipment involved in the "improvement" of real property. The "term improvement" has been given a fairly liberal definition and includes real or proposed physical changes to real property including the construction, reconstruction, alteration, repair, demolition or removal of any building or structure, any addition to any building or structure, or any construction or fixture necessary or appurtenant to a building or structure for use in conjunction therewith. It also includes excavation, digging, drilling, draining, dredging, filling, irrigation, land clearance, grading or landscaping (N.J.S.A. 2A:44A-2).

As indicated above, a lien claim filed under the CLL is to be filed against the owner's interest in the property. As an additional statutory allowance, a lien claim can similarly be filed against a tenant who has contracted for work to be performed for the improvement of the property. Such a claim will only apply to the tenant's interest except in the event that the owner has provided written authorization for the improvement. In such event, the claimant may file the lien claim not only against the tenant's lease hold interest but also against the owner's interest in the property.

Finally, with regard to a private non-residential lien under the CLL, a potential lien claimant is entitled to, but is not required to, file a "Notice of Unpaid Balance and Right to File Lien" (NUB) (N.J.S.A. 2A:44A-20). The statutes provide the form that is to be used by a potential claimant for the NUB. The NUB, as with the lien claim itself, is to be filed with the Clerk of the County in which the property is located. The NUB need not be served upon the owner or contractor but if so served, should follow the same procedures of personal or certified mail service as pertain to a lien. What will show of record does not constitute, in and of itself, a lien upon the owner's title or interest of the property. The NUB provides a benefit to a prospective lien claimant by again creating a document that, if served upon the owner and resulting in payment by the owner can allow the claimant to such a direct payment without jeopardy to the owner. It further provides the benefit of allowing the owner to have notice of a potential lien claim.



RESIDENTIAL LIEN CLAIMS

The most dramatic change in the law following the adoption of the CLL is that the CLL now prescribes a precise process for construction liens on residential properties (N.J.S.A. 2A:44A-21). Under the preceding Mechanic's Lien Law, residential and commercial properties were treated identically. Under the CLL, while the basic provisions apply to both commercial and residential private projects, additional steps must be taken by a lien claimant from a residential project. While there has not been significant litigation in which the courts have provided a great deal of direction, the statutes define a residential construction contract as including any written contract for the construction or improvement of a one- or two-family dwelling, or any portion of the dwelling, which shall include any residential unit in a condominium… any residential unit in a housing cooperative, any residential unit contained in a fee-simple townhouse development, any residential unit contained in a horizontal property regime… and any residential unit contained in a planned unit development." (N.J.S.A. 2A:44A-2). It has not yet been determined whether construction work performed on common elements such as drainage, streets, etc., in a residential development prior to constructing the actual dwellings falls within a commercial or a residential project.

Where the project is within the definition of a "residential construction contract" several additional steps must be taken by the lien claimant to assure that its lien is properly filed and perfected including:

1. A NUB must be filed and served upon the owner and intermediate contractor/subcontractor.

2. At the time that the NUB is served upon the owner and contractor/subcontractor, a Demand for Arbitration under the American Arbitration Association program that has been specifically created for residential construction lien claims must be filed, a copy of the demand similarly served by personal service or certified mail upon the owner and contractor/subcontractor.

3. The arbitration action may proceed on the documents or with a hearing but is to be promptly scheduled before a single arbitrator for the express purposes of determining whether or not the claimant is entitled to file a lien claim. The proceeding is not for the purposes of determining whether or not the owner or intermediate contractor/subcontractor may have viable defenses to the claim, but simply to determine whether the claimant is entitled under the Statute to file a lien claim.

4. Upon issuance an Arbitration Award that affirmatively finds that the claimant is entitled to file a lien claim, the claim must be filed with the Clerk in the County in which the property is located and served upon the owner as well as the contractor/subcontractor, as the case may be.

5. All of the above must still occur within the requisite 90 days from the provision of the last work, services, material or equipment. The time is not extended as a result of having to through the arbitration process. Accordingly, on a residential project, a potential claimant must decide quickly that it intends to start the lien claim process to assure that sufficient time exists to file and serve the NUB, serve the Demand for Arbitration, have the arbitration hearing and to file the lien claim all within the 90 day limit.




MUNICIPAL MECHANICS LIEN

In August 1996, the Municipal Mechanics Lien Law (MMLL) in the State of New Jersey underwent substantial changes that will have a significant impact on the ability of a subcontractor or supplier to be afforded protection under the lien provisions (N.J.S.A. 2A:44-127, et. seq.).

As under the previous New Jersey Statutes, a separate method of protecting amounts due to subcontractors and supplier existed on a public project. The lien to be established would apply only to funds remaining under the prime contractor's contract balance, and would not apply to the real estate. A Notice of Lien Claim is to filed with the public owner with a copy to the prime contractor, from whom the debt is owed. Upon receipt of such a notice, the public owner may not make further payments to the prime contractor as such sums may fall due. The owner has the rights to hold up any further payments to the contractor unless and until the lien claim is satisfied or the contractor posts a bond in double the amount of the lien claim.

The owner, upon receipt of such a notice, is to provide a ten day notice to the prime contractor to provide the opportunity to respond or object to the lien amount. If no such response is received, the public owner is entitled to release the funds sought by the lien claimant. If the prime contractor provides a response, objecting to the amount or basis of the lien claim, no funds may be released by the owner to the claimant, and the owner pays the contractor, only at its own peril, as such sums may fall due. The owner has the right to hold up any further payments to the contractor unless and until the lien claim is satisfied or the contractor posts a bond in double the amount of the lien claim.

It is notable that in the event of multiple Municipal Lien claims being filed, whose value exceeds the amount of contract balance, the ultimate distribution between the lien claimants is left at the discretion of the Court, without chronological priority.

The MMLL applies only to public entities which are not instrumentalities of the State (i.e. counties, municipalities, boards of education and their authorities).

Under the MMLL, prior to the revisions, the lien could be filed at any time after the work was performed or materials supplied until a point of sixty (60) days after the time that the project is either completed or accepted by the public agency. (N.J.S.A. 2A:44-132). As such, the subcontractor or supplier normally had a substantial period of time in which to attempt to collect its funds from the contractor prior to resorting to the lien claim procedure. It is this portion of the MLL that has undergone substantial change.

Under the amendments, any person now seeking to assert a lien must, within twenty (20) days of the first performance of work or delivery of labor or materials to a subcontractor, file with the appropriate representative of the public agency, written notice that he or she has furnished labor or materials to the subcontractor. This statute provides for a number of items that must be included within that notice including the normal information regarding the identification of the claimant or the subcontractor to whom the materials for labor has been furnished as well as a more detailed description of what has been furnished and the date that it was first supplied. Failure to provide the written notice within 20 days of the first performance of such work or delivery of labor and materials shall constitute a bar form securing a lien unless there is money owing from the contractor to the subcontractor to whom labor or materials were provided. In such case, the lien would be limited in value to a sum not greater than the money owed it form the contractor to the subcontractor.

A further caveat exists where a notice is filed after the 20 day period, the person filing may still assert a lien for labor or materials provided on or about the fling date. No additional notice is required for work or materials provided under the contract subsequent to the initial notice even if there is a separate contractor or purchase order involved.

It should be noted that this new statutory mechanism does not pertain to a subcontractor in direct relationship to the prime contractor but only pertains to suppliers or subcontractors to the subcontractor.

Although not specifically pertaining to lien claims, the same legislative act which adopted the above revisions provided similar additional requirements to a beneficiary of a payment bond that may be required for a public contracting work. Under the recently enacted provisions, any person who is a beneficiary of the payment bond and who does not have a direct contract with the contractor furnishing the bond shall, prior to commencing any work, provide written notice to the contractor by certified mail or other method whereby there would be proof of delivery, that said person is a beneficiary of the bond. Failure to provide such written notice would bar any bond claim benefits for work occurring prior to the date of the notice.

Another change to the Payment Bond Law provides that a beneficiary (here a subcontractor or lower tier subcontractor/supplier) has within a period of time of the expiration of one (1) year from the last date of performing work or delivering materials to furnish a statement of the amount due to the surety. Thereafter a 90-day hiatus period exists before a legal action can be commenced against the surety. Under the revisions, there no longer exists the requirement that the commencement of legal action must await the acceptance eof the building work or improvement by the owner. In addition to waiting the 90 days, the actin must be brought within 1 year after the beneficiary completes its work. Therefore, including the 90-day hiatus period from the time of submitting the Notice of Claim, the subcontractor or supplier seeking a claim on a bond must commence the process within 275 days of the completion of work.
 


 

 

FedEx Ground's independent contractor dispute is set to heat up this year as lawsuits make their way through the courts.

The legal issue is whether linehaul and pickup and delivery drivers are independent contractors or employees.

>>More....

3000 Midlantic Drive • Suite 200 • Mt. Laurel • NJ • 08054
Phone: (856)824-1001 Fax: (856) 824-1008

Copyright © 2007 Cureton Clark. All rights reserved. | Site by: nGravis