Cureton Caplan  
Home About Us Consultation Attorneys News Contact Us
CONSTRUCTION LIEN LAW IN NEW JERSEY NEW DEVELOPMENTS AND SPECIAL CONSIDERATIONS
By: James H. Landgraf

Following the adoption of the New Jersey Construction Lien Law in 1994 to address liens on private projects and for the following six years, what little case law arose created a pattern of strict construction.

The Courts in interpreting cases arising out of the Construction Lien Law followed the general proposition that had been prevalent under the preceding Mechanics Lien Law in that lien rights were a statutory creation and parties wishing to enjoy the statutory benefits were required to strictly comply with the provisions of the lien law.

Gallo v. Sphere Construction Corp., 293 N.J. Super. 558

(Ch. 1996)

Strictly enforcing the provisions of N.J.S.A. 2A:44A-2, 3, 9 and 10 that lien rights under the Construction Lien Law were conditioned upon the existence of a written contract, the Court rejected a lien that was filed based on work performed while a contract was being negotiated, where the contract never was formally executed and the parties terminated the relationship.

The Court also strictly construed the provisions of N.J.S.A. 2A:44A-6 which required execution of the lien by claimant or, in the case of a partnership or corporation, a partner or duly authorized officer thereof” in rejecting a lien that had been executed by counsel for the claimant similar to what was standard practice under the Mechanics Lien Law.

Finally, the Court strictly construed the requirements of N.J.S.A. 2A:44A-3, 9 and 10 by rejecting in any event the lien claimant’s attempt to seek profit on work that was not performed based upon the language that allowed a lien to be filed on the basis of work that was performed.

F. Bender v. Joseph L. Muscarelle, Inc., 304 N.J. Super. 282 (App. Div. 1997)

In this case, while the Court did not directly deal with the provisions of the Construction Lien Law, it did find that based upon the provisions of the Construction Lien Law, including the provision that prohibits a waiver of lien rights (N.J.S.A. 2A:44A-38) a subcontractor could not bypass contractual privity requirements to declare it had failed to perfect its lien rights by raising a quantum meruit claim against the owner.

Mansion Supply Co., Inc. v. Bapat, 305 N.J. Super. 313 (App. Div. 1997) cert. denied 153 N.J. 49

In Mansion, the Court strictly interpreted the “90 days from the last day of work” requirement of N.J.S.A. 2A:44A-6 in rejecting an effort to file a lien claim after that time period had passed and further determined that a filing of a Notice of Unpaid Balance consistent with N.J.S.A. 2A:44A-20, while protecting a subsequently filed lien’s priority pending the filing of the lien, would not serve to extend the 90 day requirement for the actual filing of the lien.

Orefice v. ADR, 315 N.J. Super. 493 (App. Div. 1998)

By 1998, the Courts were starting to address issues pertaining to nuances and practical complications surrounding the Construction Lien Law. One of the problems that was arising dealt with the requirements of the lien law to file action for enforcement in the Superior Court which was often contrary to contractual arbitration clauses. The Court in Orefice acknowledged this apparent discrepancy and, citing the provisions of the Construction Lien Law which allow for separate actions (N.J.S.A. 2A:44A-14d) noted that a party who made claims for relief outside of enforcement of the lien would not be precluded from doing so in a separate action and further that the lien requirement of initiating of action in the Superior Court would prevail over arbitration. This has led to the practical remedy of bringing the action within the Superior Court and then staying the same to allow for arbitration of the underlying contractual disputes, which results would thereafter return to the Court as part of the enforcement action.

Groesbeck v. Linda, 321 N.J. Super. 349 (App. Div. 1999)

Again, interpreting N.J.S.A. 2A:44A-14d, the Court determined that although the contractor had failed to property exercise its lien rights, it could still maintain a contract claim.

By 2000, the Courts in seeing Construction Lien Law cases on a more frequent basis, as well as more such cases winding their way to and through the appellate process, the Courts began to apply more practical considerations beyond the overall “strict construction” process that had applied to the earlier cases. Issues were now more frequently arising with regard to the amounts of the liens in question, the propriety of the sanction provisions and the problems associated with the “lien fund.”

Thomas Group, Inc. v. Wharton Senior Citizen Housing, 163 N.J. 507 (2000)

This case had started under the strict construction processes whereby the trial court and Appellate Division had rejected the lien. Upon reaching the Supreme Court, however, the Court began to analyze what was really at stake and issue. In this case, the primary issue dealt with the amount of the lien and whether or not the contractor had overstated the amount of the lien. The contractor had filed a lien at a point when it had performed a majority of the physical work on the project but had not turned over all required closeout documents that would have triggered the release of retainage. The lien claim included the retainage amount. The Supreme Court determined that the provisions under N.J.S.A. 2A:44A-3 that included performance of work “in accordance with the contract” was intended to mean that a party must perform work under the contract to be entitled to a lien, but did not necessarily require that the party must satisfy all terms and conditions of the contract. Veering from the “strict construction” interpretative rules that had been applied up until this time, the Court specifically determined that the statute needed to be “construed sensibly and in furtherance of the underlying legislative purpose.” The Court went on to find that in lieu of a full discharge of the lien where work and/or administrative requirements remained, a remedy could be fashioned whereby the lien claimant would be stayed in enforcing its lien until it met the contractual preconditions for payment.

Legge Industries v. Joseph Kushner Hebrew Academy, 333 N.J. Super. 537 (App. Div. 2000)

This is the first case dealing with what has become a significant practical consideration pertaining to the “lien fund.” Since the statute both provides and intends that an owner not be required to pay more than its underlying contractual obligations, the issue of what is to happen when the cumulative liens exceed the owner’s contract balance has become a common development. The Court in Legge was faced with a situation whereby the owner was holding a contract balance less than the cumulative liens. However, it was also determined that the owner had made payments to the prime contractor before they were earned and due. The Court in determining what would thereafter constitute the lien fund determined that such unearned payments would not reduce the owner’s maximum liability. The lien fund would also include contractual retainage whether or not it was earned.

The Legge Court was also asked to make a determination regarding the viability of some of the liens that had been filed. On the one hand, it reverted to the more strict reading of the “written contract” requirements pertaining to suppliers whereby delivery tickets could satisfy the writing requirement but that generalized invoicing would not. It also become the first Court to analyze what was truly allowed for under the sanction provisions of N.J.S.A. 2A:44-15. The Court determined that the requirement of “willful overstatement” as the basis for requiring forfeiture of a claim requires an intent to recover that to which the claimant knows he is not entitled. To the requirement of “willful overstatement” the Court essentially included a requirement that the claim be made in bad faith.

Triple R Enterprises, Inc. v. Pezotti, 344 N.J. Super. 31 (App. Div. 2001)

In another “lien fund” case, the Court determined that under the statutes (N.J.S.A. 2A:44A-10), the amount of the lien fund would be established at the time a lien claimant filed its lien against the owner. In Triple R, a lien had been filed by another subcontractor prior to the subject lien and payments had been made by the owner following the filing of that lien but before the subject lien. However, the initial lien had been satisfied and the additional payments where made prior to the subject lien filing. Since the prior lien had been satisfied, it would no longer count as the initiating point for developing the lien fund to protect subsequent lien claimants.

AEG Holdings, LLC v. TriGems Builders, Inc., 347 N.J. Super. 511 (App. Div. 2001)

In another “lien fund” case, the Appellate Division in determining that the construction lien statute was remedial and designed to guarantee security for those who furnish labor or materials and should be “construed sensibly,” found that a property owner was required to pay the subcontract the difference between the contract price and the amount that it had previously paid to the general contractor prior to the filing of the lien even if that resulted in the owner’s having to pay more for the finished job than the original contract price. Again, as in the case of Legge, the Court found that the owner had made payments to the general contractor which had not yet been earned by the general contractor and therefore could not be deducted from the “lien fund.”

West Virginia Steel Corp. v. Sparta Steel Corp., 356 N.J. Super. 398 (App. Div. 2003)

This case represented a “return to form” of the strict construction interpretations that had been prevalent during the early years of Construction Lien Law cases. A manufacturing supplier had filed lien claims against the project owners and thereafter commenced action in a county other than the county where the property was situated. Despite argument that rules pertaining to venue allow for relaxation of venue in the interest of judicial economy, the Court strictly construed the provisions of the Construction Lien Law (N.J.S.A. 2A:44A-14) which required the commencement of an enforcement action to be brought in the Superior Court in the county in which the real property is situated and rejected the proposition that other counts in the complaint properly placed venue in the initial county and/or the matter could be transferred.

The Court further rejected the manufacturer’s lien claim on the basis that it did not have “an agreement….” in writing. While the lien claimant had a written contract, there were no written contracts between some of the interceding parties which effectively broke the required chain of written contracts.

D.D.B . Interior Contracting, Inc. v. Trends Urban Renewal Association, Ltd., 176 N.J. 164 (2003)

Returning to the trend of “sensible interpretation,” the Supreme Court again reversed the Appellate Division’s affirmation of a trial court decision that followed the “strict construction” interpretative process. The trial court and Appellate Division, following the thought process from Gallo v. Sphere Construction Corp. with regard to who may sign a lien claim under N.J.S.A. 2A:44A-6, rejected a lien that had been signed under a “power of attorney vesting an attorney-in-fact with the authority of a duly authorized officer.” The Supreme Court found that on the basis of the properly executed power of attorney it effectively created a “duly authorized officer” and therefore even though the signatory on the lien was not a formal officer of the company, execution of the lien by the “attorney-in-fact” was sufficient to meet the statutory requirements.

Sovereign Bank v. Silver Line Holdings Corp., 368 N.J. Super. 1 (App. Div. 2004)

In the first reported case dealing with priority of liens, the Court confirmed that a first filed mortgage had absolute priority over a second filed construction lien in a foreclosure action brought by the mortgagee. The Court did note and recognize that the lienor had rights under the provisions of pertaining to Notices of Unpaid Balances under which it could have protected its priority against a mortgage that was filed in the interceding period between the NUB and the lien, but had failed to do so.

Craft v. Stevenson Lumberyard, Inc., 179 N.J. 56 (2004)

In a slight reversion to strict construction of the lien law, the Supreme Court in Craft dealt with the dual issues of the validity of a lien claim and establishing the lien fund. The Court repeated its prior statement from The Thomas Group in clearly stating that the Construction Lien Law “is not to be strictly construed, but rather is to be read sensibly and with an understanding of the policies underlying the Construction Lien Law.” The Court confirmed that an individual lien claim by a subcontractor or supplier can never be greater than the amount that that claimant is owed and that the measure of the lien fund never exceed the difference between the total contract price between the owner and the contractor and the amount that the owner has paid to the contractor as of the filing of the lien claim. The Court dealt, on a first impression, with the provisions of N.J.S.A. 2A:44A-37 which allow a property owner to request from the prime contractor, a list of all parties who may have lien rights.

Under somewhat unique factual circumstances, the Court was faced with a supplier/lien claimant who had maintained several open accounts with its customer (the contractor) and when it had received funds from the contractor, had applied them to other existing accounts that it had with the contractor. The Court determined that where the subcontractor knew that the payments were from the specific project owner and were intended to discharge duties for that project, the project owner had the right to expect that his payments would be applied for those specific materials. The Court specifically determined that the practice known as the “payment application rule” which allows a creditor to apply payments to a debtor’s account in any manner that it chooses unless otherwise instructed, is not absolute in the context of the Construction Lien Law. On this basis, the Court found that the lumber subcontractor was precluded from filing a lien claim under the Construction Lien Law where it had received but had failed to properly allocate the contractor’s payments. The Court noted that consistent with the provisions of the lien law, the subcontractor still had common law claims against its customer, the contractor.

Finally, the Court determined that in this particular instance, no lien fund existed where the project owner had made progress payments to the contractor for work performed and was fully current to the time that the contractor had left the project without paying its subcontractors. The Court thereby determined that since the owner had paid all monies actually owed, no lien fund existed.

Kvaerner Process, Inc. v. Barham-McBride Joint Venture, 368 N.J. Super. 190 (App. Div. 2004)

Following a ruling by the trial court in which a subcontractor’s lien was discharged and the general contractor was awarded counsel fees (N.J.S.A. 2A:44A-14), the Appellate Division confirmed that the general contractor was permitted to bring an action to discharge a lien and that the burden of proof would be placed upon the subcontractor to justify the claim. The Court further determined, however, that “great care” needed to be exercised in evaluating the sufficiency and good faith of the claims and that the fee and cost assessment authority provided for under the Construction Lien Law should be used conservatively to discourage premature challenges. Although not ultimately deciding the merits of the case, the Appellate Division reversed and required that the subcontractor be provided with full discovery in order to allow it the opportunity to shoulder the burden of proof.

Labov Mechanical, Inc. v. East Coast Power, LLC, 377 N.J. Super. 240 (App. Div. 2005)

In another construction lien fund case, where several subcontractors instituted construction lien actions, the Court determined that the contract balance/lien fund was not subject to reduction by liquidated damage back charges that the owner contended existed against the prime contractor, where the liquidated damages were not established until after the liens had been filed.

Riggs Distler & Co., Inc. v. Valero Refining Co., N.J. 2005 WL 2897483 (D.N.J. 2005)

The United States District Court used this case as an opportunity to revisit the provisions of N.J.S.A. 2A:44A-9 and 10 which provide the formulae for establishing the maximum amount of a lien. The Court interpreted and found that where subcontractors outstanding balance while being less than the balance remaining due from the owner to the prime contractor [strike that] where a sub-subcontractor’s outstanding receivable while being less than the amount still owed by the owner to the prime contractor, was less than the amount owed by the prime contractor to the subcontractor (contracting party with the lien claimant), the maximum amount of the lien would be limited by the amount due from the prime contractor to the subcontractor since that was the lowest in the chain of contract balances.

 

 

FedEx Ground's independent contractor dispute is set to heat up this year as lawsuits make their way through the courts.

The legal issue is whether linehaul and pickup and delivery drivers are independent contractors or employees.

>>More....

3000 Midlantic Drive • Suite 200 • Mt. Laurel • NJ • 08054
Phone: (856)824-1001 Fax: (856) 824-1008

Copyright © 2007 Cureton Clark. All rights reserved. | Site by: nGravis