|
In the previous editions of “Getting
Paid” we discussed
contract “red flags”
dealing with
situations where
proposed contract
terms require close
attention,
renegotiation or
perhaps walking away
from the prospect of
entering into a
particular project.
This edition
presumes that
contract terms have
been accepted by
both sides and a
form of contract or
subcontract has been
signed by both
sides. When an
effort to assure
proper contract
terms problems may
still arise during
the course of a
project and will be
compounded directly
or indirectly by the
failure of the
parties to abide by
the specific
contract terms that
they entered. This
may be a result of
failing to read the
contract terms,
thinking that these
terms are simply
“boilerplate;”
failure to
understand the
contract terms; a
misplaced effort to
informally resolve
issues in the field
which at a later
date creates
problems; or any
number of other
factors.
Contract terms, even those that are
looked at as simple
“boilerplate” are in
a contract for a
purpose. They define
the relationship of
the parties, they
define rights and
obligations of the
parties and they
define procedures
that are to be
employed by the
parties to enforce
those rights or
obligations. In a
later dispute, a
mediator, arbitrator
or court will look
to whether or not
the parties followed
the procedures that
they had
contractually agreed
to. If they did not,
valuable rights may
be lost, obligations
that were not
intended to be
accepted may be
imposed and what was
deemed “simple
boilerplate” may
ultimately control
the outcome of the
dispute.
If you have taken your time at the
point of initial
contracting to read
and understand the
contract terms and
to negotiate certain
terms, it makes
little sense to
proceed through the
course of the
contract ignoring
those terms. While
careful attention
should be given to
each and every
contract term (again
it would not be
there if it was not
intended to perform
some function)
particular concern
and attention must
be given to the
following categories
of contract terms.
It is incumbent on
the parties to
comply with those
terms if they wish
to protect
themselves and/or
enforce rights to
which they are
entitled under the
contract.
A.
Contractor Notice
Provisions:
Whether a contract
is a standardized
AIA, AGC or other
form document or
whether it is
customized for a
particular project,
it will include a
number of provisions
regarding the giving
of notice. It will
identify when
notices are to be
given, to whom they
are to be given, the
form of the notice
and may identify
what the content of
the notice should
be. Failure to give
a written notice may
relieve the other
party of
responsibilities,
may constitute a
waiver or release of
your invocation of
rights under the
contract or may
result in your
accepting and
assuming certain
obligations which
you never intended
to assume. Careful
attention must be
given to the notice
provisions and your
field personnel as
well as your office
personnel need to
follow the notice
requirements. Notice
provisions exist
through out the
contract but some of
the more common
requirements include
the following:
§
A contractor’s
notice to the owner
of unforeseen site
conditions
§
A contractor’s
notice to the owner
of changes in the
work
§
A contractor’s
notice to the owner
of design errors,
omissions or
discrepancies
§
A contractor’s
notice to the owner
of an intent to file
a claim for
increased costs
§
A contractor’s
notice to the owner
of a request for
time extension
§
A contractor’s
notice to the owner
of interferences
with its work by
separate contractors
or other parties
§
A contractor’s
notice to the owner
of its intent to
terminate or suspend
performance
The above referenced notices apply
similarly to
contractor/subcontractor
notices as well as
to instances where
the notices are
being provided to or
by the architect,
construction manager
or other owner
representative. To
try to limit
problems associated
with Notice
requirements, the
following steps are
recommended:
§
Review and make a
check list of when
written notice must
be provided
§
Include the timing
of notice
requirements on the
checklist
§
Develop an internal
calendar or tickler
on when Notices are
given and when
responses , if any,
are required
§
Where a notice is
issued, but goes
unanswered, send at
least one written
follow-up
§
Train both office
and field personnel
of the need to
comply with written
notice provisions
§
Where inadequate
time exists to issue
a formal notice
prior to
performance of work,
at least issue a
written confirmation
of the event
§
Maintain supporting
records of events
including written
notices, written
confirmations,
references from
meeting minutes,
time and material
records of cost
increases/changes
§
Make sure that the
written notices are
factual, neutral and
non-inflammatory in
language and cite to
the particular
contract provision
upon which the
notice is issued
B.
Responding to Owner
Actions:
Similar to the
above, the Owner or
contractor above you
will have its own
Notice requirements
preceding or
following given
events.
Additionally, it may issue notices,
directives or
instructions which
require action or
response by you.
These may include:
§ Owner’s
notice to the
contractor for
payment withholding
§
Owners notice to the
contractor to
correct rejected
work
§
Owner’s notice to
the contractor for
contractor’s default
or neglect to
carry out work and
owner’s right to
carry out the work
§
Owner’s notice to
the contractor to
stop the work
§
Owner’s notice to
the contractor of
rejected work
§
Owner’s notice to
the contractor for
termination for
convenience
§
Owner’s notice to
the contractor for
termination for
cause
§
Owner’s notice to
the contractor for
suspension
§
Owner’s notice to
the contractor as a
work directive
§
Owner’s notice to
contractor’s surety
Failure to respond in action or in
writing to such
communications may
result in the
unintentional waiver
of contract rights.
If as an example,
you are advised of
“rejected work”, a
verbal statement of
disagreement
followed by
performance of the
demanded corrective
work and then a
billing for the same
months later or as
part of litigation
may be ineffective
in protecting your
rights to
compensation.
Further, silence can
be seen as
acquiescence. You
must remain alert
and diligent in
assessing when you
are being requested
to perform work or
alter existing work
contrary to, or at
odds with your
specific contract
responsibilities.
Even if there is no
immediate impact on
compensation or
schedule, any
request to alter the
scope of your
contract work needs
to be memorialized
and responded to,
even if it is a
simple confirmation
that you have been
asked to do “X”
instead of “Y” and
are doing so. At a
later date, a
question may arise
about whether and/or
why something was
done that is not
specifically
consistent with
plans and
specifications and
you may need to show
that what is in
place was at the
directive of the
owner, architect or
others above you.
While there may be
occasions where
emergent conditions
require a waiver or
suspension of some
of the formalities
of the contract,
those instances
should be the
exception as opposed
to the rule. Some
preventative
measures include:
§
Maintain not only a
checklist for
affirmative Notices
as described above,
but also of timing
for responses
§
Send a written
confirmation of
every change or
directive given in
the field
§
Periodically review
the above writings
to see if you need
to update or
supplement a
particular written
confirmation (i.e. –
the original
confirmation
identified that you
were told to do “X”
as opposed to “Y”,
but this not has
presented some costs
or complications
which need to be
identified)
§
When you receive a
notice or directive
from the owner,
architect or your
customer, review the
contract terms
regarding the
particular notice to
determine whether a
response is needed,
timing of a response
and content of a
response.
§
Again – make sure
that both field and
office personnel are
aware of what is
occurring and what
the formal
requirements are.
Many contractors and subcontractors
either do not like
to spend their time
doing
letter-writing, or
fear that they will
poison the
relationship if they
are constantly
issuing letters and
claims. Failure to
do so, however, may
run contrary to
contract
requirements or may
result in a silent
void in response to
an otherwise costly
directive from
above. In either
event, rights may be
lost, new and
unexpected
obligations assumed,
and the ability to
be paid for work
performed
jeopardized.
You have been dealt a hand of cards when you signed
the contract. On the
basis of your
pre-contractual
negotiations, you
may in fact have
been able to arrange
so that you were
dealt certain cards.
You are now in a
game where the
contract terms
represent the rules
of the game. All
that remains is for
you to play the hand
that you have been
dealt. Your failure
to do that may
result in your
losing and
forfeiting some of
the very cards that
you fought so hard
to receive, while
you watch the bets
in the middle of the
table be swept away.
CURETON CLARK, P.C.
James H. Landgraf,
Esq. |