|
PUBLIC
CONTRACTING ISSUES
2009 found the
Courts continuing to
refine the
parameters of public
bidding
requirements. Of
significant note,
they potentially
expanded areas of
protests to allow
attacks by
non-bidders in the
form of prospective
suppliers who could
challenge the
propriety of
specification,
rejected SDA
determinations on
the weighting on
“factors” and added
mandatory equipment
disclosure lists to
the category of non-waivable
material defects.
In what could be
considered a
significant
approving comment,
or alternatively as
an inconsequential
“aside” the
Appellate Division
gave potential
credence to a school
board defense to a
claim for extras
based on the
regulatory
provisions limiting
claims for extras to
work incorporated
within change
orders.
NONBIDDING
SUPPLIER CAN
CHALLENGE
SPECIFICATIONS
Jen Electric,
Inc. v. County of
Essex (197NJ
627, NJ Supreme
Court, 2009)
In a
decision that could
greatly expand the
scope of bid
protests, the Court
found that a
material supplier,
who was not in the
position of a
bidding or potential
bidding contractor,
had standing to file
suit to challenge
the propriety of bid
specifications under
NJSA 40A:11-13(e).
The Court found that
the statutory
provision’s focus
was on timing for
the challenge, not
on who had standing
to challenge. The
Court found that
plaintiff’s role as
a prospective
supplier of “equal,
alternative
equipment” had
sufficient stake to
challenge the
specifications. The
Court limited its
holding to a
specification
challenge, finding
that a post-bid
protest on the award
of a contract
remained limited to
bidders, prospective
bidders and
taxpayers.
SDA MUST ANNOUNCE
WEIGHT GIVEN TO
DECIDING FACTORS
Van Note-Harvey
Associates, P.C. v.
New Jersey Schools
Development
Authority (407
NJ Super. 643, App.
Div. 2009)
On an
appeal by Plaintiff
of the Defendants
determination to
exclude Plaintiff
from the list of
approved soils
consultants eligible
to provide site
studies, the court
modified the
decision of the
Authority. The
selections had been
made on a “points”
basis created from
both written
submissions and
technical proposals
and then an
interview (on which
the Plaintiff
apparently fared
poorly). The Court
found that the
regulations
pertaining to the
selection process
did not identify the
weight, if any, to
be given to personal
interviews and
therefore the SDA
acted improperly in
developing their
final selections.
Faced with a need to
fashion a remedy,
the court was
concerned over how
to avoid the time,
cost, delays and
other problems that
would be associated
with re-doing the
entire selection
process or
compelling an
“award” to the
Plaintiff (since
being on the
approved list does
not guarantee any
specific projects).
The court went with
the “practical”
solution of
expanding the
approved list from 7
to 8 with would then
include the
Plaintiff (the
court does not say
what this does for
those in positions 9
and 10 who also may
have been affected
by the interview
factor).
ANNOUNCED
MANDATORY BID
REQUIREMENTS ARE
NON-WAIVABLE
Falasca
Mechanical, Inc. v.
Gloucester County
Improvement
Authority, et. al.
(App. Div. June
2009)
In this
public bidding
dispute, the Court
upheld the lower
court rejection of
two bid challenges.
On a multiple prime
contractor project,
the low bidders’
bids for plumbing
and mechanical were
each rejected by the
owner for claimed
non-waivable defects
in the bids. In one
instance, not all
subcontractors were
listed, nor were
business
registration
certificates
attached for all
subcontractors and
in the second,
business
registration
certificates were
missing. The court
determined that even
though not
statutorily
required, where
these were included
as mandatory bid
requirements the
owner was entitled
to reject bids that
lacked the
certificates. The
court found no abuse
of discretion in
either mandating the
inclusion or in
rejecting the bids.
The court also
rejected the
argument that the
specifications were
confusing and vague,
as there had been no
pre-bid protest
under the Local
Public Contract Law.
$1.45 JUDGMENT
AGAINST BOARD UPHELD
– REGULATORY
LIMITATION ON
CHANGED WORK
ENTITLEMENT RAISED
AS DEFENSE
APS Contractors
Inc v. School
District of the
Chathams (App.
Div. April 2009
Unpublished)
In this
appeal from a $1.45
million verdict in
favor of the
contractor against
the school district
on claims for
changed and extra
work, the Court was
faced primarily with
issues dealing with
the expert report
submitted by the
Defendant School
District. One of
the collateral
issues dealt with
the District’s claim
that the trial court
and jury should not
have considered
claims for extra
work by the
contractor that were
not identified
within approved
change orders. The
District argued that
by statute and
regulation, the
contractor could
ONLY proceed with
changed or extra
work following
issuance of a change
order ((NJSA
52:27BB-32; NJAC
6A:23-7.1: and NJAC
5:30-11.2 et.
seq). While
not deciding the
substance of this
position, the court
gave this defense a
level of credence by
observing it was
being rejected since
it had not been
raised in pleadings
or at trial. The
court found that
where the District
tried “its case
without pleading a
statutory defense
that may have been
available to it as a
public school
district, a
post-trial motion is
too late to raise
that defense for the
first time.”
OWNER EQUIPMENT
LIST DEEMED
MANDATORY AND NON-WAIVABLE
Cioffi”s Towing
Service, Inc. v.
Borough of
Collingswood, et.
al. (App. Div.
October 2009
Unpublished)
Although not a
construction case,
this bid protest
decision adds a new
bid requirement into
the “material, non-waivable”
category of bid
defects. Where the
municipality had
included certain
equipment
requirements in the
bid and the bidder’s
list of equipment
owned fell short of
the required items,
the Court found that
the bid would be
disqualified. The
court determined
that the bid failed
both “prongs” of the
required analysis.
First, the
municipality would
lose the assurance
that the required
equipment would be
available.
Secondly, the bidder
would have a
competitive
advantage over other
potential bidders –
some of whom may
have declined to bid
due to the lack of
the needed equipment
– since its
financial
outlay/capital
investment would be
less than others.
The court noted that
the bid solicitation
included the
mandatory language
of “shall meet the
minimum
requirement…”. The
Court found that
neither the
municipality nor it
could later
“transform the
mandatory
requirement in [the]
specifications into
a polite request”.
CURETON
CLARK, P.C.
James H. Landgraf, Esq.
|