|
There will be instances when you have
the upper hand in
dictating some of
the contract terms.
There will also be
occasions where you
have legitimate,
supportable and
enforceable claims
whether it be for
extra compensation,
for a time extension
or for a back
charge. In these
instances, there is
always an urge to
stretch the
advantage. This urge
must be carefully
controlled.
Contract Terms:
Owners, including
public owners who
have the ability to
prepare the initial
draft of the
contract terms and
in the public arena
have the ability to
dictate what the
contract terms will
be, often reach the
unfortunate opinion
that the more
one-sided the
contract terms may
be, the better off
they will be. This
attitude is also
often found in
general contractors
who include onerous,
one-sided terms in
their subcontracts
and present them to
subcontractors on a
“take it or leave
it” basis. The use
of particularly
one-sided contract
documents can
backfire on several
levels.
One-sided contract terms can run afoul
of statutory
prohibitions and be
rendered void and
unenforceable
including:
§
Indemnification
clauses that require
the lower tiered
party to indemnify
the controlling
party for all
actions including
the controlling
party’s own
negligence in
violation of
N.J.S.A. 2A:40A-1.
§
A provision
requiring that the
subcontractor and/or
supplier waive all
lien rights under
the New Jersey
Construction Lien
Law (private
projects)
N.J.S.A. 2A:44A-38.
§
The inclusion of a
general “no damage
for delay” clause in
a public contract by
the public owner in
violation of
N.J.S.A. 18A:18-41
(Board of
Education);
N.J.S.A. 40A:11-19
(Local Public
Contracts).
§
A “pay if paid”
clause or a “pay
when paid” clause in
a subcontract that
provides no
reasonable endpoint
for when the
subcontractor is
entitled to receipt
of funds earned.
The above clauses which may be placed
into a contract but
subsequently found
unenforceable. Other
clauses that place
huge insurance
requirements on the
lower tiered party,
which place full
responsibility for
unforeseen or
covered conditions
upon the contractor
or subcontractor or
which attempt to
place all risk upon
one party can also
backfire. The party
assuming the risk
may not be
financially capable
of that level of
risk resulting in a
forced default
against an “empty
pocket.” In other
instances, the party
assuming the risk
will not be
providing the most
advantageous pricing
since they need to
price for excess
risk. Accordingly,
if the price is
escalated as a
result of the
contractor having to
assume all potential
responsibility for
unforeseen
conditions, where no
adverse conditions
are encountered,
that contractor will
have received a
monetary windfall
for the assumption
of a risk that never
came to bear. It may
have be more
economically
advantageous for the
owner or general
contractor to allow
a formula for
addressing actual
adverse conditions
that may be
encountered and for
more evenly spacing
the risk.
Claims:
A second set of
situations where a
party may press a
perceived advantage
is in the processing
of claims. Most
contracts and
subcontracts have
provisions
addressing changed
work that may allow
for changes in
compensation and/or
time extensions.
Ideally, these
provisions are built
into the contract to
allow a fair
resolution so that
no party is
disadvantaged.
In an instance of overreaching, a
contractor or
subcontractor may
have a perfectly
valid basis to seek
additional
compensation and/or
a time extension due
to, by example,
changed conditions
on the site.
Anticipating that
any claim that is
made will be subject
to negotiation, that
contractor or
subcontractor then
inflates the claim.
Thereupon a “self
fulfilling prophecy”
occurs in that the
owner or general
contractor receiving
the claim will now
have no alternative
but to reject and
then perhaps start
at a level well
below what might be
due and owing. Time,
energy and effort is
spent, good will is
lost and the
relationship takes
on unnecessary
adversarial aspects.
Instead of reaching
a quick resolution
based upon a fair
pricing, no monies
are paid while the
parties position and
reposition
themselves on what
become more
intractable yet
often unsupportable
claims. Where the
claim is going to a
public entity, the
inflated claim may
also violate the
New Jersey False
Claims Act (N.J.S.A.
2A:32c-1)
resulting in not
only rejection but
also sanctions.
This same mentality may strike where
the owner or general
contractor has a
legitimate basis for
a credit or back
charge but instead
of simply providing
a reasoned and
supportable monetary
claim, all payments
are stopped or other
draconian steps are
taken leading to the
same adversarial
impasse. In the
worst instances,
unpaid contractors
or subcontractors
then walk off the
project or are
financially forced
into default.
Further, owners or
prime contractors
who commit acts that
will give rise to a
claim under the
New Jersey Prompt
Payment Act (N.J.S.A.
2A:30A-1)
allowing a
contractor or
subcontractor to
seek additional
sanctions.
In conclusion, legitimate efforts to
spread construction
project risk are
appropriate but at a
certain point where
risk is onerously
forced upon only one
side, the bet may
well exceed the
value of the cards.
Similarly,
legitimate claims
for time or
compensation and
legitimate back
charges are well
within reason under
a normal
construction
contract or
subcontract. While
you may win a hand
or two on a naked
bluff, overreaching
a perceived
advantage on a claim
seldom plays to
anyone’s benefit.
CURETON
CLARK, P.C.
James H. Landgraf, Esq. |